In a November 19, 2026 report, bitcoin miner Hyperscale Data said in a regulatory filing that its Michigan AI data center project still needed $74.8 million in spending from November 2026 through March 2027. The company warned that its existing funds and available financing would not cover planned spending and obligations over the following 12 months, raising substantial doubt about its ability to continue as a going concern.
As of the end of September, Hyperscale Data had $17 million in unrestricted cash and $231 million in current liabilities. Since late July, it had sold about 1,113 BTC for approximately $74 million. The project’s estimated construction and equipment cost was $122.1 million, of which $47.3 million had been paid by October.
The company’s agreement with an AI customer had a potential value of up to $1.2 billion—not a guaranteed payment. That figure depended on the customer renewing twice and Hyperscale Data meeting its obligations. The filing’s immediate issue was whether the company could fund the work needed to pursue that conditional opportunity.